Eleven days. That's how long Nvidia went without Jensen Huang as its chief executive.

And on the day he came back, a fuel cell company with no direct Nvidia deal jumped more than eighteen percent. Tells you who's really holding the buildout together.

You're listening to The Data Center Daily. It's Tuesday, November 24th. I'm Sarah, Matt's with me. Coming up: Huang's return and the energy companies riding on it, Southwest Power Pool's large-load filing finally on the record, PJM's board staying quiet past the advocates' deadline, and a gas wave building in the ERCOT queue.

One tap on follow, and we'll be back in your ears before you know it.

Yifan Yu, Cheng Ting-fang and Lauly Li, writing in Nikkei Asia:

As Nvidia employees clapped and cheered Jensen Huang's return as chief executive to its Silicon Valley headquarters, the supply chain that the AI chipmaker has led was still grappling with his sudden, dramatic restoration.

Where it stands. Huang resigned on November 12th amid allegations involving a suspected Chinese spy, as Latitude puts it; China has denied the espionage claims. On Monday he was back. Nvidia's board statement cites, quote, input from senior levels of the United States government. And Trump told CNBC on Monday, quote, I spoke to them, let me put it that way. And I convinced them.

One week ago, board chair Harvey Jones was using the earnings call to try to put Huang's departure behind them. Now the White House is taking credit for the rehire. That's not a succession plan, that's a phone call.

Latitude says reporting suggests Trump appeared at the board meeting to lobby for him. Keep that as reporting, not a confirmed account. The market didn't wait for details. Nikkei has Nvidia shares up more than thirty percent on November 23rd. And Latitude Media makes the energy-side point: direct financing, guarantees and backstops have made Nvidia a major player in powering data centers. It tracked the spillover: Constellation up six percent, GE Vernova up more than eight, and Bloom Energy up more than eighteen, even though Bloom has no direct relationship with Nvidia. It's marketing fuel cells to match Nvidia's chip roadmap.

That's the part that matters for this audience. Nvidia isn't just the chip vendor anymore, it's the backstop. Back on the November 17th quarter we went through it: a hundred eighteen billion dollars of guarantees, a hundred five billion of that for PORTS-Pike. When one executive's personal life moves the stock of a fuel cell maker, you're looking at concentration risk.

Latitude says Huang's personal dealmaking earned him the nickname the bank of Huang, with bets on startups like Cloverleaf Infrastructure, Emerald AI, ThinkLabs and Redwood Materials. Last week, an executive at an energy company with Nvidia investment told Latitude, on background, that tech companies have been over-dialed on the founder and CEO.

And the founder's answer is a pep talk to cheering employees: he's going to be a better CEO the second time around. Great. None of those guarantees got any smaller while he was gone.

Back to Nikkei for the caveat: Nvidia's Asian suppliers gave the return a cautious welcome, with concerns lingering over tightening US export restrictions on chips for China. A new CEO doesn't change the export rules we've been tracking.

Andry, writing at Digital News USA, on Southwest Power Pool's answer to FERC:

SPP proposes a Load Safe Harbor Limit (LSHL) that would cap Base Plan funding through its transmission rates for new or modified load delivery points at the lesser of $500,000/MW of requested demand or $25 million per request.

There it is. On Saturday we flagged that SPP's filing still hadn't shown up on the docket. It turns out SPP filed Friday, November 20th, its deadline, which makes it the last of six grid operators to respond to FERC's June 18th show-cause orders.

The cost piece, in numbers. Regional rates cover upgrades up to the lesser of five hundred thousand dollars a megawatt or twenty-five million per request. Anything above that is assigned directly to the requesting customer for up to forty years, backed by financial guarantees that shrink as the assets depreciate. The requested effective date is February 17th, 2027.

And here's the line I'd frame: the obligation applies whether or not the load is ever energized. So if a speculative hall never shows up, the developer is on the hook, not the ratepayers. MISO asked for twenty years of revenue commitments. SPP's direct assignment runs up to forty.

The other half is a new non-firm product, Price Adaptive Load Service, or PALS. Terms run one to ten years on existing transmission capability, no network upgrades needed. Participating load bids are capped at twenty-five dollars a megawatt-hour, and the load gets dispatched to zero when the local price goes above that. SPP simulated caps from twenty to thirty-five dollars. Going from twenty to twenty-five raised the simulated real-time load factor from forty-five to sixty percent and added twenty cents to the average LMP. Thirty dollars would have added another eighty cents.

Sixty percent load factor. Nobody's parking a frontier training run on that. A flexible inference shop, maybe a miner. But at least it's honest: PALS carries no extra resource adequacy obligation, and it sits below firm service and CHILLS in curtailment priority. The catch is timing. Implementation is targeted for the second quarter of 2028.

One planning detail: CHILLS and PALS loads would come out of the firm-load forecasts SPP uses for transmission planning. That matters because the board's 2026 transmission plan, approved November 17th, has peak demand going from about 58 gigawatts this year to 72 by 2030, and 96 to 110 by 2035.

Priya Raman, writing in Fracmoo, on the deadline the ratepayer advocates set PJM's board:

They asked for a written answer by November 23. As of this morning, there is no public answer. The auction is sixteen days from opening. Silence is itself an answer: a board that misses its own deadline has told the market the auction will run.

For context: on November 18th, eight advocate offices in seven states asked PJM's board to seek FERC approval to postpone the 2029/30 base auction. That's the one that opens Wednesday, December 9th, and closes December 15th. As of Monday morning, Raman found no public reply. She also says the final planning parameters, due November 19th, aren't visibly posted. PJM's capacity page still listed the October 29th report.

So the auction clears against the October numbers. A reliability requirement of 158,712 megawatts, a forecast peak of 171,916, and a cap of $337.83 a megawatt-day. The market monitor says the demand curve still carries more than 20,000 megawatts of forecast data center load. And 4,017 megawatts of the forecast increase, forty-two percent, was already canceled or delayed as of September 21st.

PJM spokesman Jeffrey Shields told Utility Dive the cap is an important safeguard against how high prices can rise, and that postponing could destabilize the market. Raman's response: the cap limits price, not quantity. Her math puts a cap-level clear at the reliability requirement at roughly 19.6 billion dollars for the delivery year. PJM also disputes the monitor's 29.4 billion dollar figure, saying it does not equate to the total cost to load.

Fair, it's a counterfactual. But the July auction cleared at its cap everywhere and still came up 6,831 megawatts short. So households pay the cap price and still don't get the full requirement. That's the part ratepayers end up paying for.

The flip side is the advocates' weak spot. The board can't move the auction on its own; only FERC can. And their alternative, the backstop procurement, isn't ready. Its target is roughly 630 megawatts, with bids March 1st through 28th of 2027. Results from the December auction post on December 22nd.

Brian at Energy News Texas, working from ERCOT's latest monthly operational overview:

Natural gas power plant requests in ERCOT’s generation interconnection queue reached 95,032 MW as of October 31, 2026, nearly double the 47,848 MW a year earlier, according to ERCOT’s monthly operational overview.

The speed is the story. Sixty-five gigawatts at the June board update, eighty in September, ninety-five by Halloween. That's roughly thirty gigawatts of gas requests in four months. Gas went from about eleven percent of the queue to almost twenty-one.

Meanwhile batteries fell almost nine percent, to about 160 gigawatts, and solar fell four percent, to about 152. They still hold about two-thirds of the queue. On the demand side: 9,456 megawatts of large loads approved to energize, with an observed October peak of 5,115 megawatts from those loads. A year earlier those numbers were 7,502 and 3,960. ERCOT also set an October demand record of 81,487 megawatts on October 13th.

Put that next to the roughly twenty-six gigawatts of permitted on-site gas we talked about last week, and Texas is going gas on both sides of the meter. My question is the usual one: who's building the pipelines, and who's waiting in the turbine line? Every one of those requests needs fuel arrangements and equipment that's already backed up.

And the standard queue caveat, which the piece spells out: these are requests to study a connection, not construction. The whole queue is 461,414 megawatts, several times ERCOT's record demand, and the inactive list grew to 169 projects. Read it as where developer money is heading, not as an in-service schedule.

If the Nvidia part of today's show is what grabbed you, we have a sister show that covers the model side of the stack: AI News for Builders, by Lantern.

It covers top AI news for engineers, founders and investors, every weekday, and it separates real capabilities from demo hype, quickly. Search for AI News for Builders, by Lantern, wherever you're listening now.

On our list for this week: whether PJM's board puts anything in writing before the auction opens on December 9th, and whether SPP's forty-year direct assignment holds up once intervenors start weighing in.

And whether Nvidia's guarantees look any different with Huang back in charge.

We'll pick it up tomorrow. The Data Center Daily comes to you from Lantern Podcasts. Thanks for spending part of your Tuesday with us.