Huang Returns to Nvidia and Energy Stocks Rally; SPP Caps Upgrade Costs for Large Loads; PJM Board Lets Advocates' Deadline Pass; ERCOT Gas Requests Double
Tuesday, November 24, 2026 · 13 min

Jensen Huang is back as Nvidia CEO after 11 days, and power and grid stocks tied to the company rallied with it. Southwest Power Pool's large-load filing puts a cap on upgrade costs and offers interruptible service, PJM's board let the advocates' Monday deadline pass without a public answer, and gas requests in ERCOT's queue have nearly doubled in a year.
Listen
Show notes
In this episode
- Asia's Nvidia suppliers give cautious welcome to Huang return - Nikkei Asia — YIFAN YU
“As Nvidia employees clapped and cheered Jensen Huang's return as chief executive to its Silicon Valley headquarters, the supply chain that the AI chipmaker has led was still grappling with his sudden, dramatic restoration.”
- Six Grid Operators Respond to FERC With Distinct Plans for Large-Load Integration - Digital News Usa — Andry
“SPP proposes a Load Safe Harbor Limit (LSHL) that would cap Base Plan funding through its transmission rates for new or modified load delivery points at the lesser of $500,000/MW of requested demand or $25 million per request.”
- The Deadline Is Today. PJM's Board Has Not Answered — and the November 19 Parameters Changed Nothing Anyone Can See | Fracmoo — Priya Raman
“They asked for a written answer by November 23. As of this morning, there is no public answer. The auction is sixteen days from opening. Silence is itself an answer: a board that misses its own deadline has told the market the auction will run.”
- ERCOT Gas Plant Requests Double to 95 GW – Energy News Texas .com — Brian
“Natural gas power plant requests in ERCOT’s generation interconnection queue reached 95,032 MW as of October 31, 2026, nearly double the 47,848 MW a year earlier, according to ERCOT’s monthly operational overview.”