Nvidia's interim CEO spent a surprising share of last night's call talking about land, power and shell. Not wafers. Not memory. Buildings with electricity. Which tells you where the line outside the door actually starts. This is The Data Center Daily, Wednesday, November 18th. I'm Sarah, and Matt is across the table. On today's list: Nvidia's quarter and the commitments behind it, the Federal Reserve's first look at data center leverage, the cost recovery agreements MISO filed Monday, and Texas regulators restarting data center permits. Follow the show and the next briefing lands in your feed on its own.

Colette Kress, Nvidia's interim CEO, on Tuesday's earnings call, from the transcript Investing.com published:

Our outlook considers data center readiness, the strength and durability of end customer demand, and our customers’ access to capital.

The top line first. Revenue was 115.8 billion dollars for the quarter ended October 25th, up 103 percent on a year ago, and 107.6 billion of that was data center. Guidance is 130 billion, plus or minus 3 percent. Nvidia raised its fiscal 2028 growth outlook to about 75 percent, from 70, and guided gross margin down to 71 to 72 percent, which Kress called the bottom. Two asterisks on that guide. The fourth quarter has an extra week, and Sean at SOTKN works it out to about 9.3 billion dollars a week against 8.9 this quarter. Call it 4 percent, not the 12 the headline suggests. And the guide assumes zero data center compute from China. Kress said Nvidia sold 2.4 billion dollars of licensed Hopper products there in the quarter and is no longer shipping them. She didn't say why. Chairman Harvey Jones opened by saying the board does not intend to reinstate Jensen Huang, and announced a new National Security and Export Control Oversight Committee. For this audience, the commitments are the story. Per InfotechLead's read of the CFO commentary, purchase commitments rose to 390 billion dollars from 279, mostly multiyear memory agreements, with 203 billion falling due in fiscal 2028. Data center lease and cloud service commitments went to 102 billion from 74. Then guarantees: 118 billion dollars maximum, 105 of it credit support for SB Energy's PORTS-Pike campus in Ohio, leased to OpenAI for 20 years, with capacity coming online in phases from calendar 2028. Bernstein's Stacy Rasgon asked about a new sentence saying neocloud commitments only take effect if those neoclouds secure financing. Kress's answer: the guarantee starts when the site is ready. If the build is delayed or runs into trouble, the guarantee doesn't exist. She said nothing about the practice is new. And the cash. SOTKN reports receivables of 81 billion dollars, up about 18 billion in one quarter, with days sales outstanding moving from 60 to 64. Nvidia cites Rubin shipment timing and extended payment terms for certain investment-grade customers it didn't name. The 10-Q is due in the coming weeks. Put it together. Allocation goes to customers whose land, power and shell are ready, per Kress. Guarantees only switch on once the building is. The world's biggest chip seller just told you its scarce input, and it isn't a chip.

Nick Lichtenberg at Fortune, on the Federal Reserve's November Financial Stability Report:

The new section counts more than $1 trillion in leases that are signed but haven’t started yet, plus more than $2 trillion in take-or-pay contracts and residual value guarantees, at Amazon, Alphabet, Broadcom, Meta, Microsoft, Nvidia, and Oracle.

That section, titled Leverage in the Data Center Buildout, is new. None of the five earlier editions going back to 2024 had one. Fed Governor Michael Barr, speaking in Milan on Monday, put the potential maximum nominal value of those obligations above 3 trillion dollars, and said the seven firms' on-balance-sheet debt is expected to pass 800 billion by year-end. The Fed itself warns the off-balance-sheet figures are undiscounted and not directly comparable with debt. The part I'd underline is where the risk ends up. Developers finance construction against those leases, and the riskier slices sit with high-yield funds, life insurers, BDCs and private debt vehicles. The largest US bank holding companies have close to a trillion dollars of exposure across big tech, developers, AI special purpose entities, private credit and utilities. Barr's warning was that the opacity can make selloffs worse, because nobody can tell where the risk sits. The issuance side: debt tied to advanced computing topped 680 billion dollars by October, about five times all of 2023, and is roughly 31 percent of nonfinancial investment-grade issuance this year. Of 23 market contacts the Fed surveyed, 87 percent named AI as a salient risk, up from 50 percent in May. Barr did say he's less worried about direct bank losses, given how little debt backs the boom so far. Now a live one. Dan Rabb at Bisnow, citing Bloomberg, reports HSBC sold 300 million dollars of construction debt on Project Jupiter in Doña Ana County, New Mexico, for less than 90 cents on the dollar. It's a piece of an 18 billion dollar, 20-bank package for the Stack Infrastructure campus being built for Stargate, up to 2.45 gigawatts. HSBC reportedly sold right after Oracle sent the developers a force majeure notice in September that would let it defer payments if the project slips. ING is reportedly shopping 25 million of its own exposure. Bisnow adds that some data center project bonds now yield in the double digits and credit default swaps on data center debt are at an all-time high. Read alongside the SemiAnalysis revision we covered yesterday, the pattern holds: the spending stays big, and financing it gets more expensive. The Fed's next report is due in the spring.

Owen Hollis, writing in Load Factor News:

In FERC Docket ER27-526, MISO and its transmission owners propose a $250,000 application, security equal to upgrade capital cost and a yearly true-up for the utilities that serve large loads.

Yesterday we couldn't confirm a complete MISO response to FERC's show-cause order. This is it, filed Monday, and it's the cost recovery piece MISO had promised. Every transmission request for a load of 50 megawatts or more goes through a single Large Load Project Review, three cycles a year, about five months each. Only the transmission customer, usually the serving utility, can apply, and the megawatts can't change after filing. The money mechanics. If the owner rolls an upgrade into zonal rates, the customer owes a 20-year revenue commitment covering return, depreciation, operations and taxes. Each year MISO compares that number with the transmission revenue the load actually produced and bills the shortfall. MISO's own shorthand: a 10 million dollar commitment against 7 million of revenue means a 3 million dollar check. Security equal to the upgrades' capital cost is due within 45 days of signing. The owners' witness ran an illustrative case, not a real project: a 500 megawatt load, 100 million dollars of upgrades, a 20-year fixed charge rate of about 13.7 percent. That's roughly 274 million in total, about 13.7 million a year once everything is in service. For scale, MISO says load requests approved in its 2026 transmission plan averaged 145 million dollars of upgrades each. And the data center signs none of it. MISO calls the transmission customer merely a pass-through in many cases and leaves it to the states to push costs further down. So whether the hyperscaler pays depends on a retail tariff filed somewhere else. The companion filing, ER27-527, is GRITS, the permanent flexible service FERC asked for. A load picks a firm slice. The rest is interrupted when its price tops 100 dollars a megawatt-hour, which MISO says historically would have allowed service in more than 95 percent of hours, and a capacity advisory cuts the whole non-firm portion. New England set its line at 250. The catch is timing: the earliest start is January 1st, 2029, and the rates aren't filed yet. Answers in MISO's show-cause docket are due December 16th, and SPP still owes its filing on Friday. My watch item is the one Hollis flags. State regulators asked whether an upgrade that gets folded into a later regional project still carries the data center's name. This filing doesn't answer that in so many words.

Emily Foxhall at The Texas Tribune:

State environmental regulators have resumed reviewing data center permits, bringing an end to an earlier directive from Gov. Greg Abbott ordering a pause on permit approvals related to data center projects.

A correction to the frame we used yesterday, when Latitude's reporting had lifting the permit freeze falling to Governor-elect Gina Hinojosa. On the environmental side, that's no longer the case. TCEQ got notice from Abbott's office on Friday that ERCOT had finished gathering information on community impacts, and the agency says it has resumed its normal permit review. Abbott had ordered that pause in a September 21st letter. And it didn't wait long. Ariel Wittenberg at Politico reports TCEQ issued an air permit on Monday for SpaceX's 24 billion dollar data center and gas-fired power plant in the Rio Grande Valley, the Texas campus we covered on Saturday the 14th. That came three days after environmental groups filed a complaint alleging SpaceX had begun construction without a permit, in violation of the Clean Air Act. Public Citizen's Kathryn Guerra says TCEQ is issuing permits without sharing ERCOT's findings with communities or explaining how it will use them, and the group called on the commissioners to resign. ERCOT told the PUC on November 5th that 93 percent of 465 projects responded, enough for a statistically meaningful analysis. Full findings go to the PUC on December 10th, ahead of the December 17th open meeting. Keep the two freezes straight, though. This is TCEQ, so air and stormwater permits. Abbott's August pause on grid interconnection approvals is a separate order, and the Tribune doesn't report that one lifting. So SpaceX has an air permit for its turbines, and the queue question still runs through December. For anyone holding a Texas air or stormwater application, the practical read is a window that runs until a new governor takes office January 19th.

If today's Nvidia segment left you wanting the other half of that story, there's a sister show for it. Jensen Huang Investigation Watch is a daily on the Nvidia CEO news: the board probe, Congress, Megaspeed and China chip exports, sorted by what is confirmed, alleged and denied. Search for it wherever you found us. That new export control committee is squarely their territory.

We're back tomorrow, Thursday, a day before SPP's large-load filing is due, with whatever shows up in the MISO and PJM dockets in the meantime. Read the CFO commentary tonight. The guarantees live in the footnotes. The Data Center Daily comes to you as a Lantern Podcast. I'm Sarah, that was Matt, and we'll talk tomorrow.