Nvidia Guides to $130 Billion and Ties Its Guarantees to Ready Sites; Fed Finds $3 Trillion Off Balance Sheet; MISO Files Cost Recovery; Texas Restarts Permits

Wednesday, November 18, 2026 · 13 min

The Data Center Daily cover art

Nvidia's first quarter under an interim CEO beat and raised, but its commitments, receivables and guarantees now hinge on land, power and shell. The Fed put AI data center leverage in its stability report, MISO filed its large-load cost recovery agreements, and Texas regulators resumed data center permits.

Listen

Listen to the audio episode

Read the episode transcript

Show notes

Nvidia's first quarter under an interim CEO beat and raised, but its commitments, receivables and guarantees now hinge on land, power and shell. The Fed put AI data center leverage in its stability report, MISO filed its large-load cost recovery agreements, and Texas regulators resumed data center permits.

In this episode

  1. Earnings call transcript: NVIDIA tops Q3 2026 estimates and lifts outlook By Investing.com — Investing.com
    “Our outlook considers data center readiness, the strength and durability of end customer demand, and our customers’ access to capital.”
  2. Fed’s first close look at AI buildout finds $3 trillion of commitments off Big Tech’s balance sheets | Fortune — Nick Lichtenberg
    “The new section counts more than $1 trillion in leases that are signed but haven’t started yet, plus more than $2 trillion in take-or-pay contracts and residual value guarantees, at Amazon, Alphabet, Broadcom, Meta, Microsoft, Nvidia, and Oracle.”
  3. MISO Files Its Promised Cost Recovery Agreements: Data Center Hosts Owe 20 Years of Revenue on Upgrades, Whether or Not the Load Shows Up | Load Factor News — Owen Hollis
    “In FERC Docket ER27-526, MISO and its transmission owners propose a $250,000 application, security equal to upgrade capital cost and a yearly true-up for the utilities that serve large loads.”
  4. Texas officials resume environmental permits for data centers — Emily Foxhall
    “State environmental regulators have resumed reviewing data center permits, bringing an end to an earlier directive from Gov. Greg Abbott ordering a pause on permit approvals related to data center projects.”