Thirty-one million dollars down, fifty-nine installments to follow. Finally, a data center customer paying for capacity before the capacity exists.
That's out of TVA's annual report, and it's where we start. This is The Data Center Daily for Sunday, November 29th. I'm Sarah, here with Matt. After TVA: Nomura says Rubin racks slip into 2027, Jera shops its gas plant sites to US hyperscalers, and a North Texas city votes Tuesday on whether it can handle any more data centers.
Paul Ciampoli of the American Public Power Association, reading TVA's annual report:
The Tennessee Valley Authority on Nov. 10 entered into a Capacity Commitment Charge agreement under which TVA is entitled to receive aggregate payments of $1.7 billion.
Per the 10-K, that's 31 million dollars at signing, then 59 installments. The charge took effect October 1st for new and expanding data center loads above 5 megawatts, at roughly 1.5 million dollars per megawatt of requested capacity above that line. The customer is unnamed.
Do the napkin math. If all 1.7 billion were capacity charge at that rate, you're in the neighborhood of a gigawatt of requested load. TVA doesn't disclose the size, so that's arithmetic, not reporting. Either way, a customer is putting real money down at signing. I like that a lot.
Grid and Generation ties the tariff revenue to the 1.5 gigawatts of new gas TVA's board approved in August, targeted for 2032, with up to another 3.1 billion possible on that project. The same report says TVA holds the first NRC construction permit for a small modular reactor, a BWRX-300 at Clinch River.
Two caveats. TVA says the rate reflects its current cohort pricing and may be revised for future cohorts, so the next customer could pay something different. And TVA is still evaluating the amortization period that decides how it classifies the liability. Still a better template than hoping the load shows up.
Diego Almada Lopez, writing in Crypto Briefing, on a new Nomura note:
Nomura’s Taipei tech team, led by Anne Lee, has trimmed its 2026 supply forecast for Rubin and Rubin Ultra chips by 19%. Its estimate fell from 2.02 million units to 1.63 million units. The same team is now more optimistic about 2027, and it credits a single customer with the change: SpaceX.
Rack numbers: NVL72 cut to 60,000 from 62,000 for 2026, raised to 75,000 from 66,000 for 2027. Nomura points to three bottlenecks. HBM4 yields, TSMC advanced packaging capacity, and heat from denser systems.
Heat. Every slide deck says liquid cooling is solved, and the analyst note says thermals are pushing deliveries into next year. If you're a colo developer who promised a customer a Rubin-ready hall for late 2026, you may be carrying empty space for a quarter.
The demand side is the striking part. Nomura cites SpaceX plans to go from about 3 gigawatts of compute at the end of 2026 to more than 13 by the end of 2027, and projects SpaceX, xAI and the neoclouds could account for 55 to 60 percent of Nvidia's 2027 rack purchases.
Yesterday we had SpaceX still chasing a permit and power agreements in Cochise County. Thirteen gigawatts by end of next year needs a lot more of those to close. Concentration risk for Nvidia, and a power-procurement problem for whoever builds for SpaceX.
Zachary Skidmore at Data Center Dynamics, following Friday's Nikkei report:
Jera, Japan's biggest energy firm, is in talks with several major US hyperscale and AI companies, including Meta and Anthropic, over plans to site data centers near power plants in the Tokyo area.
CEO Yukio Kani told Nikkei that Amazon, Google and Microsoft are in the conversation too. The template is October's deal with Dell and Rhaelm: a planned 400-megawatt behind-the-meter campus at the LNG-fired Chiba station, which has 4.38 gigawatts of output, operations expected in 2028, about 15 billion dollars across all phases.
Talks. Reuters, via The Edge, has a Jera spokesperson saying Rhaelm handles marketing and that Jera was told Rhaelm is talking to multiple hyperscalers. So it's secondhand. None of the five companies commented, and Yokohama is a non-binding MoU.
Agreed on status. The strategic logic is real, though. Jera runs more than 20 thermal plants, almost 55 gigawatts combined, and it's standardizing cooling and power modules to repeat the design across sites. A plant site already has generation and a grid tie on the fence line.
It also already has the gas bill. Yokohama talks about low-carbon supply; Chiba is LNG. If a hyperscaler signs one of these, I want to see the carbon accounting it publishes alongside.
Ahmed Humble, writing in the Houston Chronicle:
Denton city leaders are preparing to vote on a 90-day pause for new data center development as the North Texas city weighs whether its water, wastewater and electric systems can handle more of the power-hungry facilities.
The final reading is Tuesday, December 1st, and it needs three-fourths of the full council. The city's own numbers: up to 48 million gallons a day of water production against a 42.2 million peak, and a Pecan Creek plant rated at 21 million gallons of wastewater handling 25.7 million on peak days.
That's a sewer plant already over its rating. And on power, per the staff report, Denton Municipal Electric has about 75 megawatts available at transmission voltage, with no process for queuing data center requests so it doesn't get promised three times over. That's the honest version of a capacity constraint.
Scope matters. Projects with applications already filed are vested under state law and can't be stopped, and developers can seek a waiver by offering to pay for missing facilities. Core Scientific's agreement for up to 391 megawatts and the 20-megawatt Qumulus AI site were approved earlier, and staff say both pay their full power and transmission costs.
So it's a pause to write rules, not a ban. Ninety days, one extension allowed, expiring March 1st if nothing changes. I'd rather a city say we're out of sewer capacity now than discover it after the permits are signed.
If this briefing saved you some time in the dockets, a rating or a short review in your podcast app helps other grid and infrastructure people find the show.
On the calendar: Denton votes Tuesday, and we'll be listening for the first name attached to TVA's new charge.