Nvidia Reportedly Freezes Southeast Asia Server Shipments; Google Pays to Reconductor Ohio Lines (November 26, 2026)

November 26, 2026 · 8m 12s · Listen

Malaysia, Thailand, Indonesia, Singapore. Four countries where a server order apparently just stopped moving.

And the instruction reportedly came from Nvidia itself. This is The Data Center Daily, on Thursday, November 26th, Thanksgiving in the US. I'm Sarah, with Matt. Today: Nvidia's reported shipping pause, a Google reconductoring deal in Columbus, a hard-won tax break for Digital Realty outside Chicago, and Amazon swapping in a new climate yardstick.

If today's show was useful, follow us wherever you're listening — the next one will be waiting.

Ville Heiskanen at Bloomberg News, relaying a Financial Times report on what Nvidia's manufacturing partners, Super Micro and Dell among them, are telling customers:

have told buyers in Malaysia, Thailand, Indonesia and Singapore that the US giant won’t let their orders be shipped, the newspaper reported, citing people familiar with the matter. It’s unclear if the pause is temporary, the FT said.

Context from CNBC. Commerce's Bureau of Industry and Security announced an interim final rule on Monday, November 16th, aimed at Chinese companies renting advanced Nvidia chips in overseas data centers. It took effect Thursday the 19th. Trade Representative Jamieson Greer told CNBC the rules close off smuggling through places like Southeast Asia, and remote access from data centers in third countries.

And look at what's already happening to the inventory. GPU Mart's Jack Duhamel and two other sources told CNBC there's been an unusually high volume of Nvidia GPUs put up for sale since the rule, including deals floated for thousands of B300s. Somebody in that region built a hall for racks that now can't land. Who eats that lease?

Status check: this is the FT citing people familiar, Nvidia declined to comment to CNBC, and nobody knows yet if the pause is temporary. On the November 17th call, then-interim CEO Colette Kress said Nvidia was still studying the controls but expected demand to keep outrunning supply.

Three days after Jensen Huang's return, this is his first real test. Welcome back.

From Latitude Media:

Under a proposal filed last week with the Public Utilities Commission of Ohio, Google would pay $10.8 million for the utility to install advanced conductors on about 15 miles of power lines in Columbus — lines Ohio Power was already planning to rebuild. As a result, the hyperscaler said it would get access to 24 megawatts of capacity two years early as it expands a data center in the city.

Twenty-four megawatts is small. The interesting number is the seven hundred megawatts of extra headroom by 2031 versus a standard rebuild. But that depends on a separate roughly three-hundred-mile transmission project also coming online by 2031. So the big number has a dependency attached.

Right, and the mechanics matter. Advanced conductors carry forty to seventy percent more than conventional wire, and studies from DOE and from GridLab with UC Berkeley put them at thirty-three to seventy-five percent cheaper than a new line. Google's Ellen Zuckerman calls it extending the clean transition tariff from generation to transmission.

Here's what I like: the hyperscaler writes the check for the upgrade instead of spreading it across the rate base. What I'd want from the PUCO record is the split between that ten-point-eight million and the rebuild Ohio Power was already doing. Utilities earn on spending, not on squeezing more out of a corridor.

Latitude makes that point too. And FERC's show-cause orders now require grid operators to evaluate these technologies when studying transmission service, and explain when they don't use them.

Christopher Placek, writing in the Daily Herald, on Tuesday night's vote in Rolling Meadows, Illinois:

As part of the agreement, the council formally endorsed the developer’s request for a Cook County Class 6B property tax incentive, which would allow the property to be assessed at lower levels for a dozen years: at 10% of market value for 10 years, then 15% in the 11th year and 20% in the 12th year. Industrial property is normally assessed at 25%.

The project: Digital Realty's $466.9 million redevelopment of a vacant 40-acre office campus outside Chicago. The Inference puts it at 156 megawatts of critical power, fed by a 240-megawatt ComEd substation. The council voted 4-2. In exchange, the developer pays the city at least 49 million dollars through 2041.

Hundreds of residents filled the chambers and two overflow rooms, chanting "Where's our vote?" Sounds like a fun Tuesday night. Their issues were water, power bills and noise. The answers: closed-loop cooling, a sound consultant before and after construction, and diesel generators limited to outages, grid-operator orders and weekday testing.

And the city's leverage argument. Alderman Nick Budmats feared the developer would leave Rolling Meadows and annex into Schaumburg, which could grant the same break. Officials say almost all new industrial development in the area gets a 6B or a TIF district anyway.

Fine. But the timeline: construction starts by February 2029 and wraps by June 2031. That's a long wait on land Digital Realty bought in September. I'd want to know what ComEd has actually promised that substation.

Jeff Young, writing in Latitude Media:

Meanwhile, Amazon, which reported a 16% emissions increase in its most recent sustainability report, announced last week a new sustainability target built on a measure of the carbon intensity of its energy use. The company said its new aim is to reduce the carbon dioxide per unit of energy used by 65% by 2030, compared to 2019 levels.

We covered Meta's emissions report on November 21st. The new piece is Amazon. Its carbon chief, Chris Roe, says net zero by 2040 still stands, and that the path was never going to be linear, quote, and here we are.

A sixty-five percent cut against a 2019 baseline Amazon hasn't published. No current figure either; the spokesperson says those come in next summer's report. And it covers scope 2 only. NewClimate Institute's Louise Bammel says it wouldn't necessarily require absolute emissions to fall.

To be fair, Bammel also calls it an improvement on Amazon's old per-dollar-of-revenue measure, and the methodology is public. But Latitude notes the planned Pecos County, Texas project will have more than seven gigawatts of gas turbines.

Meanwhile Meta told Latitude it's re-evaluating the 2030 timeline and interim milestone, with an update promised within the year. So the targets are moving, and the turbines are still getting built.

Working one of these filings yourself, or think we misread a footnote? Tell us at datacenterdaily at lantern podcasts dot com. Corrections and tips both welcome.

Things to watch: whether the Southeast Asia pause turns out to be temporary, and what the Ohio commission does with Google's filing.