PJM and CAISO File Their Large-Load Plans; SemiAnalysis Cuts AI Capex as Much as 40%; Amazon Sets a 7% Cap Rate (November 17, 2026)

November 17, 2026 · 13m 14s · Listen

Seven percent. That's the yield Blackstone's new data center trust says it's paying for thirteen Amazon buildings, and it's now the number every listed data center landlord gets measured against. Meanwhile the analysts who drew everyone the steep curve just took a red pen to it. You're listening to The Data Center Daily. It's Tuesday, November 17th, I'm Sarah, and Matt's with me. Coming up: what PJM and CAISO actually filed with FERC on Monday, SemiAnalysis cutting its AI accelerator capex forecast by as much as 40 percent, the Amazon sale-leaseback that set that seven percent mark, and the December limbo facing Texas data centers.

Reuters, as carried by The Business Times, on what PJM filed Monday:

The biggest US electric grid operator, PJM Interconnection, said on Monday (Nov 16) it is proposing a plan to federal energy regulators to speed up the connection of power plants and the energy-intensive data centres that need them, but the proposal may require data centre companies to pay a larger share of grid costs.

Yesterday Brandon Owens reminded us a faster study isn't a faster substation. PJM has now put a number on the study part. Its Fast Energization proposal would study new generation, transmission service and large loads together instead of in separate queues, in twelve months instead of two years. PJM asked FERC for a 60-day comment period and an order within 120 days. Voltgrid News notes the docket number wasn't posted yet. And the catch is in that second clause. Readiness and financial requirements move earlier, so per Voltgrid a developer commits money before it knows the full upgrade bill. PJM also says the process would show states and utilities what data-center-driven transmission upgrades cost, so they can bill those loads directly. That's the part Reuters flags as the bigger share of grid costs. The Data Center Coalition told PJM's board in October a combined study might mean longer delays. PJM's spokesman Jeff Shields says study time is the one factor its planners can influence. For context, Reuters puts PJM's supply shortfall at about 6.8 gigawatts. The filing I'd read first is the other one. Ride-through rules for any computational load of 50 megawatts or more, proposed effective January 16th, 2027. PJM says that on July 22nd nearly 3.9 gigawatts of data centers jumped to onsite generators after a routine transmission disturbance, the largest transfer like that in its history. That's a big power plant's worth of load stepping off the grid over a routine fault. PJM serves around 10 gigawatts of that load today and forecasts up to 30 more by 2030. Out west, CAISO filed Monday too, under docket ER27-532, per Wedoany. The threshold is 50 megawatts of peak load at a single site. Its Flexible Interim Load Interconnection grants limited-capacity service before upgrades finish, with enforceable load reduction, and converts to firm once the upgrades are done. CAISO wants the main provisions effective February 16th, 2027, and says it will publish the total proposed large-load capacity alongside upgrade cost estimates. Publishing the cost estimates. Revolutionary. And I mean that, actually. Still unconfirmed in the reporting we have: NYISO's filing and a completed MISO response. SPP's board is expected to decide today, ahead of Friday's deadline.

Chase Na at VLSI Korea, working through SemiAnalysis's revised model:

Even after the cut, the 2030 forecast stands at USD 923 billion, and the hyperscalers' actual contract backlogs and spending plans have not shrunk yet. What has bent is the slope of the curve — the assumption that spending grows faster every year — not the scale of AI infrastructure investment itself.

The numbers come from a model update dated Friday, November 13th. Global AI accelerator capex for 2027 goes from 770 billion dollars to 627, down 19 percent. 2028 goes from about 1.05 trillion to 758 billion, down 28. And 2030 falls from about 1.53 trillion to 923 billion, down 40. One caveat: Na cross-checked these across secondary coverage, not the subscription-only original. The line for this audience is power. Per those reports, SemiAnalysis cut its 2030 power demand forecast by 34 percent. And in the summary Longbridge posted, the reasons read like our last three weeks of episodes. Slower net-new revenue growth at frontier labs. Tighter debt and equity markets for developers without a hyperscaler behind them. Midterm results delaying 5.8 gigawatts of planned US supply from late 2027 and early 2028. And power constraints severe enough that vendors are moderating maximum chip power targets. Then there's who absorbs the cut. Reports say Nvidia accounts for 66 percent of the reduction in cumulative 2026-to-2030 silicon shipment area, while Amazon's Trainium kept its near-term forecast and Broadcom and AMD held up relatively well. The assumed average selling price for Nvidia's Feynman generation drops from 175,000 dollars to 98,000. And this landed eleven days after the previous version of the model. Nobody redraws a curve that fast over a rounding error. The counterweight is real. UBS raised its forecast instead: one trillion dollars of global AI capex in 2026, 1.4 trillion in 2027, 1.5 trillion in 2028. Na's read is that UBS is measuring committed totals, while SemiAnalysis and Citrini, which declared peak capex growth on November 4th, are measuring the growth rate. Which is why Nvidia's report today, under an interim CEO, matters more than usual. Tom's Hardware, citing SemiAnalysis, says Nvidia's supply and capacity commitments rose by almost a quarter of a trillion dollars in a single quarter, mostly memory. If the curve bends, somebody is left holding those commitments.

Franco Faraudo, writing in Propmodo:

The 7 percent cap rate on the AWS portfolio is a real number that other developers can price against, and the 12-year initial term with a 32-year extension is a real duration that lenders can underwrite.

The deal. Per a TIKR analysis by Gian Estrada, Blackstone Digital Infrastructure Trust, ticker BXDC, announced on Monday a November 11th agreement to buy 75.1 percent of two joint ventures holding 13 newly built powered shells on AWS campuses in northern Indiana and Mississippi. The portfolio is valued at about five billion dollars and carries 647 megawatts. Amazon keeps 24.9 percent, worth about 600 million, and leases all of it back for 12 years, extendable to 32. Read the funding stack, though. BXDC puts in about 1.9 billion, and roughly 2.5 billion is new non-recourse mortgage debt. So the headline five billion is the portfolio value, not the check Amazon walks away with. Estrada works out roughly 350 million dollars of first-year rent, rising 2.75 percent a year, guaranteed by Amazon.com. As for why Amazon would sell buildings it fully intends to keep using, Faraudo points to trailing twelve-month free cash flow swinging to a 42.4 billion dollar outflow by the end of the third quarter. A sale-leaseback turns a finished building into cash while keeping the capacity. Then Jim Chanos shows up on X saying a 7 percent cap rate would value Digital Realty and Equinix materially lower than where they trade. Short seller finds something to short. But Estrada's own math is gentler. The fairer yardstick is the low-to-mid-5 percent AFFO yield BXDC's CEO Nick Pell cited, which would put Digital Realty around 18 to 20 times forward AFFO, against 22.8 today. And a powered shell is a building with a power hookup. Digital Realty runs the whole facility. Pell told Bloomberg the deal creates a roadmap for more. Faraudo's rough estimate is that close to half the capital behind the largest US projects lately has arrived through structures where the operator is a tenant, heavily weighted toward Meta. He calls the figure imprecise. My question is the one he ends on. Who holds the risk when a 12-year lease runs out on a building designed for hardware that turns over every four or five years? Meta attached residual value guarantees near 28 billion dollars to its Hyperion vehicle. Watch the guarantee terms, not the cap rate.

Lisa Martine Jenkins, writing in Latitude Media:

A project that clears the audit in December will still need for ERCOT to restart approvals and for the state to lift the permit freeze — and both of those decisions will fall on Hinojosa.

Where the queue stands, per a Latitude Intelligence analysis: ERCOT has provisionally let about 200 projects totaling 66.4 gigawatts keep their place, has shut out more than 350 projects totaling over 300 gigawatts, and nearly 170 gigawatts are still waiting. ERCOT files its verification and community impact reports on December 10th, and the current PUC meets December 17th. Then comes the handoff. Governor-elect Gina Hinojosa takes office January 19th. She campaigned on blocking new construction until lawmakers pass stronger rules on water and energy use. Abbott froze the queue with letters to the PUC, ERCOT and TCEQ, which, as Jenkins points out, means she can do the same thing. Jefferies expects a legislative compromise that codifies consumer protections rather than a reversal, but warns the pause could be long. That's the same session where SB 338, the cooling-and-water bill we covered yesterday, is waiting on a committee referral. And NRG and Vistra each fell 14 percent after the election. Now hold that next to AEP. The Inference's Vincent Jiang notes AEP tells investors it has 84 gigawatts of contracted data center load by 2031. Its CFO split it out: 35 gigawatts under firm take-or-pay agreements in PJM and SPP, and 46 gigawatts in Texas backed only by SB6 letters of agreement that obligate no one to buy a kilowatt. AEP has collected over two billion dollars of cash or collateral for Texas, and developers can recover most of it. AEP's 10-Q says ERCOT won't authorize large loads to energize until verification is complete. Texas is 55 percent of the claimed gigawatts and 17 percent of AEP's 100.4 billion dollar capital plan. So more than half the headline is a refundable deposit and a letter. December 10th is when we start finding out what it's worth.