The Data Center Daily

ERCOT’s AI Load Wave Hits the Cost-Allocation Wall

Friday, June 12, 2026 · 11 min

The Data Center Daily cover art

ERCOT’s data-center queue has ballooned to 519 large-load requests in two years, sharpening fights at FERC and in Congress over who pays for AI-driven grid upgrades as Meta locks in new power and capacity deals.

Listen

Listen to the audio episode

Read the episode transcript

Show notes

ERCOT’s data-center queue has ballooned to 519 large-load requests in two years, sharpening fights at FERC and in Congress over who pays for AI-driven grid upgrades as Meta locks in new power and capacity deals.

In this episode

  1. Texas grid slammed by 519 power-hungry AI data center requests in just two years — The Cool Down

    Texas grid slammed by 519 power-hungry AI data center requests in just two years Photo Credit: iStock Proposed AI data centers are poised to put a new kind of pressure on Texas' power system as their electricity needs climb, The Texas Tribune reported. That potential demand is arriving as the grid has come under intense scrutiny in recent years. ### What's happening? According to The…

  2. ‘Buckle up’: FERC, lawmakers grapple with data center costs - E&E News by POLITICO — POLITICO

    ‘Buckle up’: FERC, lawmakers grapple with data center costs - E&E News by POLITICO - Skip to primary navigation - Skip to main content - Skip to footer # ‘Buckle up’: FERC, lawmakers grapple with data center costs Speakers at POLITICO’s Energy Summit pressed for more government action to ensure utility ratepayers don’t bear the costs of an energy-intensive AI boom. Federal Energy Regulatory…

  3. RWE secures Meta PPA on 298-MW Texas solar project — Solar Power World

    # RWE secures Meta PPA on 298-MW Texas solar project Author: Billy Ludt Published: 2026-06-11T16:52:58+00:00 Source: solarpowerworldonline.com (solarpowerworldonline.com) Language: en ## Story RWE secures Meta PPA on 298-MW Texas solar project RWE and Meta have arranged a long-term corporate power purchase agreement (PPA) for the electricity generated by the 298-MWAC Rabbit’s Foot Solar…

  4. Reliance, Meta Partner to Build AI-Enabled Data Centre in Jamnagar, Gujarat — TelecomTalk

    Reliance, Meta Partner to Build AI-Enabled Data Centre in Jamnagar, Gujarat × ### Highlights - Reliance and Meta have partnered to develop a 168 MW AI-enabled data centre in Jamnagar, Gujarat. - The facility will be Meta's first built-to-suit data centre in India. - Reliance will provide end-to-end services, from design and construction to operations and utility management. Live #### Hardik…

  5. NVIDIA's First Co-Packaged Optics Switch Lands at Lambda, Cutting 3kW Per Rack and Freeing Power for 3,137 Extra GPUs — Wccftech

    # NVIDIA's First Co-Packaged Optics Switch Lands at Lambda, Cutting 3kW Per Rack and Freeing Power for 3,137 Extra GPUs Author: Hassan Mujtaba Published: 2026-06-11T09:05:13+00:00 Source: wccftech.com (wccftech.com) Language: en ## Story NVIDIA's First Co-Packaged Optics Switch Lands at Lambda, Cutting 3kW Per Rack and Freeing Power for 3,137 Extra GPUs # NVIDIA’s First Co-Packaged Optics…